County of Monmouth

For Immediate Release:

June 4, 2015

 

               

Oceanic Bridge work remains on schedule

Bridge will open to all traffic Friday evening though 6 a.m. Monday

 

RUMSON, NJ – Since 6 a.m. Monday morning, around the clock work to repair bearings on the south side of the Oceanic Bridge (S-31) has been under way; the work has progressed on schedule and allows for the bridge to open Friday evening through Monday morning.

“This affords us the opportunity to open the Oceanic Bridge to traffic again this weekend, from Friday evening, June 5, through Sunday, June 7,” said Freeholder Thomas A. Arnone, liaison to the Department of Public Works and Engineering. “Harms Construction has assured the County that opening the bridge this weekend will not delay the completion of the project, which is scheduled for next Friday, June 12.”

Harms Construction Co. Inc. of Howell will resume work at 6 a.m. Monday, June 7 on the south side of the structure that spans the Navesink River and connects Rumson to Middletown.  Harms crews will be working 24 hours a day, in two -12 hour shifts, to have the work completed by June 12.

The Oceanic Bridge has been closed to all but marine traffic since 6 a.m. Tuesday, May 26. For marine traffic, seasonal rules and scheduling are in effect.

“A previous Oceanic Bridge repair project revealed deterioration in two areas not readily or previously accessible,” said Arnone. “Two of the bridge’s four main bearings support the bascule and flanking spans on the bridge approaches.”

Ettore explained that the nature of the repair work requires that the bridge load be relieved by lifting the bascule and approach spans off of each bearing and that the bearing work must be completed to maintain public safety and the use of the Oceanic Bridge.

“It is prudent to lift the bridge spans and perform the repairs to all four of the bearings,” said Ettore.  “The bearings in need of immediate repair are on the eastern side of the bridge, but the County is also going to repair the bearings on the western side of the bridge.” 

Freeholder Arnone and Senator Joseph Kyrillos have worked with local officials, business and educational interests to discuss the scheduling options for the necessary work.  The post-Memorial Day closing for the three week repair project was the best of the scheduling options.

“The post-Memorial Day around-the-clock work schedule reflects a mid-June completion date,” said Arnone.

The 2,712-foot drawbridge crosses the Navesink River and serves beach, commercial and residential traffic, as well as pedestrian and bicycle travel. It is also a key route for coastal evacuations and emergency vehicles headed to hospitals or providing mutual aid. The bridge has been classified as structurally deficient.

Built in 1939, the Oceanic Bridge has deteriorated due to decades of exposure to saltwater and from accommodating heavier vehicles and traffic volumes than for which it was designed.

In 2012, Monmouth County completed extensive work to rehabilitate the bridge’s 100-foot, center bascule span, allowing motorists, bicyclists and pedestrians to continue use of the bridge.

Monmouth County received notification from the North Jersey Transportation Planning Authority (NJTPA) Board of Trustees in January that $600,000 in federal funding was available to perform a Concept Development Study for the replacement or rehabilitation of the Oceanic Bridge.

“As the years have gone on, maintaining this bridge has become more costly and difficult,” said. Arnone, a NJTPA Board member. “This grant will allow us to look to the future and take steps toward building a better bridge, one that will stand up to the extreme coastal storms we’ll face and serve our modern travel needs.”

Monmouth County plans to replace the Oceanic Bridge in the next ten years.

#     #     #